3 MW: Hybrid-EMS-Project Tangermünde
In Saxony-Anhalt, near Stendal, Frankfurt Energy Holding implemented the Graustorm BESS project in Tangermünde. For this project, meteocontrol supplied its hybrid EMS solution for connecting a battery energy storage system to the medium-voltage grid. The project focused on the intelligent control of a battery with a capacity of approximately 3 MW and a usable storage capacity of 6 MWh.
Central to the technical implementation was the seamless integration of grid operator and energy marketer interfaces to ensure grid-friendly and economically optimized operations. Precise technical planning and execution resulted in a stable system that fully met the requirements of modern energy storage applications.
System data
- Location: Germany
- Commissioning: 2026
- BESS capacity: approx. 3 MW/6 MWp
- Voltage level: Medium voltage
- Grid operator: AVACON Netz
Services
- Technical Planning and Design of the Control System
- Battery Control via the Hybrid EMS Solution for the blue'Log XC
- Integration of Grid Operator and Energy Retailer Interfaces
- Remote Commissioning
- Monitoring in the VCOM Cloud for Professional and Efficient Technical Asset Management