3 MW: Hybrid-EMS-Project Tangermünde

In Saxony-Anhalt, near Stendal, Frankfurt Energy Holding implemented the Graustorm BESS project in Tangermünde. For this project, meteocontrol supplied its hybrid EMS solution for connecting a battery energy storage system to the medium-voltage grid. The project focused on the intelligent control of a battery with a capacity of approximately 3 MW and a usable storage capacity of 6 MWh.

Central to the technical implementation was the seamless integration of grid operator and energy marketer interfaces to ensure grid-friendly and economically optimized operations. Precise technical planning and execution resulted in a stable system that fully met the requirements of modern energy storage applications.

System data


  • Location: Germany
  • Commissioning: 2026
  • BESS capacity: approx. 3 MW/6 MWp
  • Voltage level: Medium voltage
  • Grid operator: AVACON Netz

Services


  • Technical Planning and Design of the Control System
  • Battery Control via the Hybrid EMS Solution for the blue'Log XC
  • Integration of Grid Operator and Energy Retailer Interfaces
  • Remote Commissioning
  • Monitoring in the VCOM Cloud for Professional and Efficient Technical Asset Management

Image source: Frankfurt Energy Holding